Commissioning of the Pilot Plant Continues

Commissioning continues of the pilot plant, ensuring that all aspects of the equipment work correctly, in preparation for trials.

The commissioning activities over April involve:

- Test-firing of furnace burners
- Testing of each process line
- Furnace refractory dry-out
- Cold feed conveying
- Extraction system testing
- Commencement of test campaigns